Future Location

Moving Information – Update Delivery Time

Dear customers,

With reference to our letter from November 2024, we would like to provide you with an update on the expected impact on delivery times during the relocation phase.

Product group Relocation start Expected production start in Esslingen
Gear TW130/160 07.07.2025 11.08.2025
Gear TW45/TW63 02.09.2025 06.10.2025
Gear W332 22.09.2025 27.10.2025
Gearless SC400/SC500 29.09./12.10.2025 03.11./08.11.2025

During the relocation period mentioned above, no new drive production will take place.
Delivery times will be extended by up to approximately 10 weeks during this period.

In the coming weeks, the delivery times for individual series will change at short notice depending on production scheduling at the old or already established location. For time-critical projects, please contact your LiftEquip sales representative and inquire about the current capacity situation.

As a precautionary measure, we have increased the inventory levels of certain TW45/TW63 gearbox variants for urgent emergencies.

However, we would like to ask you again to consider the temporary delivery extension in your requirements planning and to submit orders to us as early as possible.

We thank you for your understanding and your proactive support in ensuring the successful relocation phase.

Best regards

LiftEquip GmbH Elevator Components